August inspection pit concrete work
- Rimutaka Incline Railway
- On Saturday morning we placed a further 3.5m3 of concrete into the inspection pit facilities under construction in our rail vehicle shed. This nearly completes the 24-metre long inspection pit wall (just 2m left at the Upper Hutt end) and we now have two of the five upper floor sections poured.Project: Rail vehicle shedRoute: Maymorn20 August 2012